Test Plan is a roadmap of our test. It defines the strategy, scope, resources, schedule, and approach to be used for performance testing.
Purpose
Define the testing strategy and approach to achieve performance objectives.
Benefit
Provides clarity to all stakeholders and ensures a structured and measurable testing process.
Who Creates
Performance Test Lead / Test Engineers
Reviewed By
Project Team, Architects, Infrastructure Team, NW Team, Stakeholders
Approval
Must be reviewed and approved before test execution.
Test Plan Components
| Component | Description |
|---|---|
| Objective of the Test | Define the goals and performance objectives of the test. |
| Scope | Define what will be tested in this performance test. |
| Items Out of Scope | Define what will not be included in the performance test. |
| Test Approach | Overall strategy and methodology to achieve the test objectives. |
| Procedure | Step-by-step activities to be followed during testing. |
| Types of Testing | Load, Stress, Endurance, Scalability, Spike, Baseline, Soak, etc. |
| CBT's (Critical Business Transactions) | List of critical transactions that will be tested with priority. |
| Test Data | Details of data required for performance testing. |
| Application Architecture | High-level overview of the application architecture. |
| Tool Architecture | Architecture of performance testing tool and its components. |
| Environment | Hardware, software, network configuration and setup details. |
| Monitoring Strategy | Metrics to monitor (CPU, Memory, Disk, Network, Application, DB, etc.). |
| Deliverables | Documents and reports that will be delivered. |
| Roles & Responsibilities | Roles of each team member and their responsibilities. |
| Risks & Mitigations | Potential risks identified and mitigation plan. |
| Prerequisites | Requirements that must be available before test execution. |
| Assumptions | Assumptions made during planning the test. |
| Entry Criteria | Conditions that must be met to start testing. |
| Exit Criteria | Conditions based on which testing will be considered complete. |
Entry Criteria
Whenever the pre-requisites are satisfied, that is called Entry Criteria.
Examples:
- Test environment is ready
- Test data is prepared and loaded
- All scripts are reviewed
- All approvals are obtained
Exit Criteria
Whenever derived statistics are meeting expected statistics, that can be considered as Exit Criteria.
Examples:
- Response times meet SLA
- System handles expected load
- Error rate is within acceptable limit
- Test objectives are achieved
Test Plan Summary
| Section | Key Details to Capture |
|---|---|
| What | What are we trying to achieve? |
| How | How the testing will be performed? |
| What to Test | Which applications, modules, features, transactions are in scope? |
| How Much Load | Expected users, transactions per second, ramp-up pattern, peak hours. |
| Where | Environment details (Servers, OS, DB, Network, Middleware, Tools). |
| How to Measure | What metrics will be captured and tools used? |
| When | Timeline for each phase of testing. |
| Who | Team members and their responsibilities. |
| Risks | Risks identified and mitigation plan. |
| Deliverables | What reports and documents will be provided? |